Bunbury Outer Ring Road - Noise Walls & Hard Landscaping
CLIENT
South West Gateway Alliance
LOCATION
Bunbury, WA
STATUS
Completed
COMPLETION
Bunbury, WA
PCH Civil delivered the installation of 6.5km of noise and screening walls and 40,000m² of concrete footpath along the Bunbury Outer Ring Road (BORR) for the Southwest Gateway Alliance, enhancing noise mitigation and visual screening for surrounding communities.
Construction of pile footings including augering, reinforcement and concrete placement
Installation of structural steel posts up to 12m high
Installation of over 1,500 precast concrete wall panels
Temporary works and support systems for safe installation
Lifting, handling and securing of precast panel systems
Delivery of 6.5km of noise and screening wall infrastructure
Placement of 40,000m² of concrete footpath to complement the road infrastructure.