Hope Downs 4 - BOO Plant Civils
CLIENT
Mineral Resources (CSI)
LOCATION
Newman, WA
STATUS
Completed
COMPLETION
Newman, WA
PCH Civil successfully delivered a major civil works package at Hope Downs 4 mine site, constructing key mining infrastructure to support ongoing operations.
The scope included:
Bulk earthworks for Plant Pad, ROM Pad and road construction
Construction of haul roads, internal roads, culverts and HV/LV safety windrows
Borrow pit management, crushing and screening of construction materials
Trenching and installation of inground services infrastructure
Construction of water storage ponds including detailed earthworks and HDPE liner installation
Site establishment including offices, workshops, storage and amenities